BMS panel upgrade 

Working for our BMS client to deliver this install on their behalf, an old panel past its serviceable life, our task was to strip out the existing panel install the new panel and work with the commissioning engineer to bring the new panel on-line within five days.

As a functioning leisure centre we are unable to switch the system of and proceed with the works so we had to form a plan for this to happen with the least amount of disruption, So for this to happen first off we set about installing a temporary distribution board so that all key plant could moved over and left on running while we carried out the works,  our second task, was that no drawings existed so we had to work through the panel and building identifying each cable for each piece of kit it was connected to..

 