Pet Store
An 8 week project to deliver the electrical package on this install, once all the final drawings had been submitted it was was time to get started on stripping out this former shoe store and turning it in to new pet store.
This was an 8 week project which included the following:
- New 3-phase distribution board
- All new containment
- Installation of 3-phase isolators
- 24hr hour dedicated power for pet enclosures
- General power
- LED lighting
- Cat5E data network
- Audio installation
- Fire Alarm
Our main contractor and ultimately the end client was extremely pleased with the works carried out and that the project was completed on time and within budget